Clause
52.211-18 Variation in Estimated Quantity.
If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an exten
- Type: Clause (C)
- Prescribed in: 11.703(c)
- Effective: Apr 1984
- Primary source: eCFR 48 CFR 52.211-18 · acquisition.gov
Text excerpt from the eCFR API; read the full clause at the eCFR link above.