52.216-4 Economic Price Adjustment-Labor and Material.

(a) The Contractor shall notify the Contracting Officer if, at any time during contract performance, the rates of pay for labor (including fringe benefits) or the unit prices for material shown in the Schedule either increase or decrease. The Contractor shall furnish this notice within 60 days after the increase or decrease, or within any additional period that the Contracting Officer may approve in writing, but not later than the date of final payment under this contract. The notice shall include the Contractor's proposal for an adjustment in the contract unit prices to be negotiated under pa

Text excerpt from the eCFR API; read the full clause at the eCFR link above.

Applicability in the matrix

Contract types for 52.216-4 as published in the Smart Matrix
IBRYes Incorporated by reference
UCFI
FP SUPO Optional
FP SVCO Optional
FP CONO Optional
T&M LHO Optional
LMVO Optional
COM SVCO Optional
DDRO Optional
A&EO Optional
FACO Optional
IND DELO Optional

Reporting, not advice

MyFCExperts reports what the official federal clause matrix says applies at a given contract type, and what each clause says and where it is prescribed. It does not determine whether a specific contract or subcontract is compliant, and nothing here is legal advice or creates an attorney-client relationship. Always read the linked primary source and consult a qualified professional for your own situation.

Follow the clause matrix without re-reading it

The clause reference is free to browse. The MyFCExperts Clause Access membership adds saved contract profiles and the nightly clause-change feed for the contract types you pin. (The full clause matrix and flow-down views stay free.).

Join for $129 one-time Create a free account