52.236-15 Schedules for Construction Contracts.
(a) The Contractor shall, within five days after the work commences on the contract or another period of time determined by the Contracting Officer, prepare and submit to the Contracting Officer for approval three copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percenta
- Type: Clause (C)
- Prescribed in: 36.515
- Effective: Apr 1984
- Primary source: eCFR 48 CFR 52.236-15 · acquisition.gov