52.236-21 Specifications and Drawings for Construction.
(a) The Contractor shall keep on the work site a copy of the drawings and specifications and shall at all times give the Contracting Officer access thereto. Anything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both. In case of difference between drawings and specifications, the specifications shall govern. In case of discrepancy in the figures, in the drawings, or in the specifications, the matter shall be promptly submitted to the Contracting Officer, who sh
- Type: Clause (C)
- Prescribed in: 36.521
- Effective: Feb 1997
- Primary source: eCFR 48 CFR 52.236-21 · acquisition.gov
Text excerpt from the eCFR API; read the full clause at the eCFR link above.