52.242-15 Stop-Work Order.

(a) The Contracting Officer may, at any time, by written order to the Contractor, require the Contractor to stop all, or any part, of the work called for by this contract for a period of 90 days after the order is delivered to the Contractor, and for any further period to which the parties may agree. The order shall be specifically identified as a stop-work order issued under this clause. Upon receipt of the order, the Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the order during the period

Text excerpt from the eCFR API; read the full clause at the eCFR link above.

Applicability in the matrix

Contract types for 52.242-15 as published in the Smart Matrix
IBRYes Incorporated by reference
UCFF
FP SUPO Optional
CR SUPO Optional
FP R&DO Optional
CR R&DO Optional
FP SVCO Optional
CR SVCO Optional
LMVO Optional
SAPO Optional

Reporting, not advice

MyFCExperts reports what the official federal clause matrix says applies at a given contract type, and what each clause says and where it is prescribed. It does not determine whether a specific contract or subcontract is compliant, and nothing here is legal advice or creates an attorney-client relationship. Always read the linked primary source and consult a qualified professional for your own situation.

Follow the clause matrix without re-reading it

The clause reference is free to browse. The MyFCExperts Clause Access membership adds saved contract profiles and the nightly clause-change feed for the contract types you pin. (The full clause matrix and flow-down views stay free.).

Join for $129 one-time Create a free account