52.242-15_Alternate I Stop-Work Order.
(a) The Contracting Officer may, at any time, by written order to the Contractor, require the Contractor to stop all, or any part, of the work called for by this contract for a period of 90 days after the order is delivered to the Contractor, and for any further period to which the parties may agree. The order shall be specifically identified as a stop-work order issued under this clause. Upon receipt of the order, the Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the order during the period
- Type: Clause (C)
- Prescribed in: 42.1305(b)
- Effective: Apr 1984
- Primary source: eCFR 48 CFR 52.242-15 · acquisition.gov