Clause
52.249-10_Alternate II Default (Fixed-Price Construction).
(a) If the Contractor refuses or fails to prosecute the work or any separable part, with the diligence that will insure its completion within the time specified in this contract including any extension, or fails to complete the work within this time, the Government may, by written notice to the Contractor, terminate the right to proceed with the work (or the separable part of the work) that has been delayed. In this event, the Government may take over the work and complete it by contract or otherwise, and may take possession of and use any materials, appliances, and plant on the work site nece
- Type: Clause (C)
- Prescribed in: 49.504(c)(1)
- Effective: Apr 1984
- Primary source: eCFR 48 CFR 52.249-10 · acquisition.gov