52.249-14 Excusable Delays.

(a) Except for defaults of subcontractors at any tier, the Contractor shall not be in default because of any failure to perform this contract under its terms if the failure arises from causes beyond the control and without the fault or negligence of the Contractor. Examples of these causes are (1) acts of God or of the public enemy, (2) acts of the Government in either its sovereign or contractual capacity, (3) fires, (4) floods, (5) epidemics, (6) quarantine restrictions, (7) strikes, (8) freight embargoes, and (9) unusually severe weather. In each instance, the failure to perform must be bey

Text excerpt from the eCFR API; read the full clause at the eCFR link above.

Applicability in the matrix

Contract types for 52.249-14 as published in the Smart Matrix
IBRYes Incorporated by reference
UCFI
CR SUPA As prescribed
CR R&DA As prescribed
CR SVCA As prescribed
T&M LHA As prescribed
FACA As prescribed
SAPA As prescribed

Reporting, not advice

MyFCExperts reports what the official federal clause matrix says applies at a given contract type, and what each clause says and where it is prescribed. It does not determine whether a specific contract or subcontract is compliant, and nothing here is legal advice or creates an attorney-client relationship. Always read the linked primary source and consult a qualified professional for your own situation.

Follow the clause matrix without re-reading it

The clause reference is free to browse. The MyFCExperts Clause Access membership adds saved contract profiles and the nightly clause-change feed for the contract types you pin. (The full clause matrix and flow-down views stay free.).

Join for $129 one-time Create a free account